The Oasis PGACSL is a wall-mounted, non-refrigerated bi-level drinking fountain with a water saver bubbler, available in Greystone, Sandstone, or Stainless Steel.
Before You Begin
- Tools: Pilot drill bit, power drill, slotted screwdriver, T15 Torx driver, bubble level, tape measure, and a tool for cutting plastic pipe. Wall anchors (8 per unit), a 1-1/4" P-trap, and a water shut-off valve are not included.
- Plumbing: Provide a 3/8" water supply with shut-off valve and a 1-1/4" IPS drain stub-out. Maximum supply pressure is 100 PSI, so install a pressure regulator if spikes could exceed that. Flush the supply line before installing.
- Electrical and ventilation: Where power is required, provide a 20A minimum GFCI-protected outlet. Allow 4" of clearance per side for ventilation.
- Safety and support: Some states require a licensed plumber, and all connections must meet local plumbing codes. Do not alter or modify the unit, as this voids the warranty and UL listing.
- Installation reference: See the installation manual for rough-in diagrams, left or right side high orientation, and detailed instructions.
Step-by-Step Installation Guide
- Plan the layout: Check the water, waste, and power rough-in locations against the manual's diagram. The unit ships right side high, and the left side high orientation needs the patch plate and drains swapped.
- Install the hanger brackets: Secure the brackets to the wall with 2 anchors each, making sure they are level.
- Hang and secure the unit: Hang it on the galvanized steel frame, not under the return edge of the stainless basin top. Remove the front panels, mark the anchor holes, drill pilot holes, and secure the unit with wall anchors.
- Connect the drain: Install the included drain components with insulation on the brass drain pipe. Connect a P-trap to the drain stub-out and basin drain, cutting the drain pipe as needed.
- Connect water and test: Connect the 3/8" copper inlet tube to the shut-off valve and secure all lines. Turn on the water, check for leaks, and run the bubbler until the stream is constant.
- Adjust and finish: Turn the adjustment knob beneath the fountain nose with a slotted screwdriver until the stream is at least 4" high per ADA requirements. Reinstall the front panels once testing is complete.