Elkay MF200 Installation Instructions & Guidance

The Elkay MF200 bi-level mounting frame is designed for in-wall installation of two-station refrigerated drinking fountains in new construction and renovation projects. Professional installation by a licensed contractor or plumber is strongly recommended to ensure proper wall framing, rough-in placement, and a secure, square installation.

Key Installation Requirements:

  • Wall opening of 37-1/2" W x 37-3/4" H, set 4-1/2" above the floor line
  • Minimum 12" depth from the finished wall face to the back of the wall
  • Wall opening reinforced on all sides to support up to 150 lbs static load
  • (12) 5/16" bolts or screws to secure the frame to the wall (not included)
  • At least 4" of air flow clearance on both sides and the top of the remote chiller
  • Plumbing rough-in and a 120V, 60 Hz, single-phase, 3-wire 10 amp branch circuit for the chiller

Important Notes Before Installing the MF200:

  • Wall fasteners are not included. The installer must supply twelve 5/16" bolts or screws for the frame and appropriately sized fasteners for the chiller shelf.
  • Decide on the standard (higher unit on the left) or reversed (higher unit on the right) configuration before framing the opening.
  • The wall opening dimensions are required for proper rim and bubbler heights under ANSI A117.1. Refer to the fountain model for final ADA compliance.
  • If the frame is placed next to a bottle filler unit, leave a double stud or 3" of space between mounting frames.
  • Make sure the frame is square, and do not use fewer or smaller fasteners than required.
  • Always refer to the official Elkay MF200 Spec Sheet for dimensions and compatibility, and to the fountain's own installation manual for unit-specific steps. Elkay notes the actual frame may vary from the one illustrated.

Basic Installation Overview:

  1. Cut a square, rectangular wall opening 37-1/2" W x 37-3/4" H, 4-1/2" above the floor line.
  2. Reinforce the opening on all sides so it supports up to 150 lbs static load and gives a way to secure the frame.
  3. Install the plumbing and electrical rough-ins.
  4. Remove the frame and hardware from the packaging, then bolt the two frames together through the upright supports with the (4) 5/16" x 3/4" bolts and nuts provided.
  5. Set the frame assembly squarely in the opening with the upright edges flush with the finished wall face, then secure it with (12) 5/16" bolts or screws.
  6. Attach the chiller shelf support rods to the right-side frame uprights at the second set of holes from the bottom and to the shelf's side holes, then fasten the shelf to the frame bottom and wall.
  7. Continue with the fountain and chiller installation according to the unit's installation manual.

For complete step-by-step instructions, download the official Elkay MF200 Mounting Frame Installation Instructions